A request for information form your team can send today, and a log that tracks every RFI from question to answer. Both are laid out on this page. The Excel file adds dropdowns, date checks, a days open count and a red flag on every answer that is late.

See the template

By CCO

What an RFI is, and when to send one

An RFI (request for information) is a written question from the contractor to the architect about the contract documents: two drawings that disagree, a dimension that is missing, a detail that cannot be built as drawn. The AIA's standard general conditions make it the formal channel. A201-2017 asks the contractor to report any error, inconsistency or omission it finds as a request for information, in the form the architect requires (Section 3.2.2), and commits the architect to answer in writing, within the agreed time or with reasonable promptness (Section 4.2.14).

Send an RFI when

  • Two documents conflict: a plan and a detail, or a drawing and the spec.
  • Information the work needs is missing: a dimension, a material, a mounting height.
  • Field conditions differ from what the drawings show.
  • A detail cannot be built as drawn and you have a fix to propose.

Do not use an RFI for

  • Proposing a substitution. That follows the substitution procedure in Division 01.
  • Getting a product approved. That is a submittal, tracked in a submittal log.
  • Pricing extra work. That is a change order request.
  • Anything the documents already answer clearly. Reviewers send those back, and they still cost time.

Why the log matters

RFIs pile up. In a 2013 research paper, the Navigant Construction Forum looked at about 1.1 million RFIs on 1,362 projects, most of them in Australia and New Zealand, and found an average of 796 RFIs per project and a median reply time of 9.7 days. From an informal survey of three US design and construction management firms, the authors estimated that a typical RFI takes about eight hours to log, review and answer, at about $1,080. With hundreds of questions open on a job, the log is the one place anyone can see which answer is holding up work.

The template: form and log

The file has two working sheets. The form is what goes out for each question; the log is the running list the whole team checks. Here is every field, with example rows so you can see how a filled log reads.

The RFI form

One page, set up to print on letter paper. Each box says what goes in it. The fields follow the minimum content the Navigant Construction Forum recommends for an RFI form, plus the No, Yes or Potentially impact choices of NAVFAC's guide specification.

Request for Information (RFI)

Project

Project name

The name used on the drawings, so the RFI files with the right job.

Project number

The architect's or the owner's project number.

RFI number

The next number in the log, in order. Never reused.

Date sentDate

The day the RFI goes out. The response clock starts here.

From and to

From (name, company)

Who is asking. On most jobs the general contractor sends RFIs, including the questions its subcontractors raise.

To (architect or engineer)

Who is expected to answer.

Email or phone

Where the reviewer can reach the person asking.

Copies to

Consultants, owner's representative or trades that need to see the question.

The question

Subject

A short title that says what the question is about, one issue only.

Spec section

The specification section that governs the work, for example 08 11 13.

Drawing and detail

The exact sheet and detail, for example A-501, detail 4.

Discipline and trades affected

Architectural, structural, MEP, and the trades waiting on the answer.

Schedule activity affected

The activity in the construction schedule that the answer holds up.

Priority (1 highest, 5 lowest)Dropdown

How urgent the answer is, from 1 (stops work) to 5 (no time pressure).

Options: 1, 2, 3, 4, 5

Response required byDate

A real date tied to the schedule. Never ASAP.

Question

What is unclear, where, and why it matters. Quote the conflicting notes if there are two.

Suggested solution

How the contractor would resolve it. Lets the reviewer answer with a simple yes.

Impact (contractor's view)

Potential cost impactDropdown

No, Yes or Potentially, said up front rather than after the answer.

Options: No, Yes, Potentially

Cost estimate, if any

A rough number if the contractor expects one.

Potential schedule impactDropdown

No, Yes or Potentially.

Options: No, Yes, Potentially

Days, if any

Estimated days of delay if the contractor expects any.

Attachments

Marked up sheets, photos, sketches. List them so none gets lost.

Response

Response

The answer itself, specific enough to build from, not a pointer to another sheet.

References

Sheets, spec sections or sketches the answer relies on or issues.

Responded by

Name and company of the person answering.

Date of responseDate

The day the answer goes back.

Does the answer change cost or time?Dropdown

The reviewer's view. A Yes means a change order, not just an answer.

Options: No, Yes, Potentially

The RFI log

One row per RFI, in number order. Days open counts itself, and the response date turns red once it passes with no answer, unless the RFI is closed, returned or void.

RFI log, with three example rows

Slide the table sideways to see every column.

RFI No.Date sentSubjectSpec sectionDrawing / detailFromAssigned toPriorityResponse dueStatusDate answeredDays openCost impactSchedule impactResolutionNotes
Example00103/02/2026Door 104: frame head conflicts with supply duct08 11 13A-501, detail 4General contractorArchitect203/09/2026Closed03/06/20264NoNoSketch SK-03 issued: duct offset above frameEmpty
Example00203/04/2026Lobby tile: grout joint width not specified09 30 13A-601General contractor (tile sub)Architect403/18/2026Answered03/11/20267NoNoAnswered in writing, to be issued as ASI 02Empty
Example00303/12/2026Embed plate at grid C/4 missing from structural plan05 50 00S-201General contractorStructural engineer103/17/2026OpenEmptyStill openPotentiallyPotentiallyEmptySteel erection waits on this
Rows marked Example are made up to show how each column is filled in. In the Excel file they sit in gray italics, ready to delete.

What goes in each column

RFI No.
Sequential number, matching the form.
Date sentDate
Day the RFI went out.
Subject
Short title of the question, one issue per RFI.
Spec section
Governing specification section.
Drawing / detail
Sheet and detail the question refers to.
From
Company that asked.
Assigned to
Who owes the answer: architect or a consultant.
PriorityDropdown
1 stops work, 5 has no time pressure.12345
Response dueDate
Date the answer is needed. Turns red when it passes with no answer.
StatusDropdown
Open: waiting for an answer. Answered: reply received, under review. Closed: answer accepted and sent to the field. Returned: sent back because it is not an RFI or lacks information. Void: withdrawn or a duplicate.OpenAnsweredClosedReturnedVoid
Date answeredDate
Day the answer came back.
Days openCalculated
Calculated: days from sent to answered, or to today while it is still open.
Cost impactDropdown
Does the answer affect cost?NoYesPotentially
Schedule impactDropdown
Does the answer affect time?NoYesPotentially
Resolution
What closed it: a sketch, a supplemental instruction, a revised sheet, a change order.
Notes
Anything the next person needs to know.

How to run RFIs that get answered fast

  1. 1. One question per RFI

    Two questions in one RFI get one answer, and the second one gets lost. The Navigant Construction Forum's best practices limit each RFI to a single subject, which also keeps the log honest: one row, one issue, one date.

  2. 2. A date, never ASAP

    Set the response date from the schedule activity the answer holds up. The RFI form Navigant recommends rules out ASAP as a response date, and its best practices ask contractors to submit RFIs at least 10 days before the answer is needed.

  3. 3. Point to the exact sheet, detail and spec section

    A reviewer who has to hunt for the problem answers it later, and sometimes answers a different one. Navigant's best practices ask for specific drawing and specification references on every RFI, and the log keeps both in their own columns.

  4. 4. Propose a fix

    When you can see a way to resolve it, write it in the Suggested solution field. The reviewer can then answer with one word, and the fix comes from the people who know the field conditions. Navigant's best practices ask for a suggested resolution whenever the contractor sees one.

  5. 5. Flag cost and time on every RFI

    Mark cost and schedule impact as No, Yes or Potentially before the answer comes back. NAVFAC's guide specification (UFGS 01 31 23.13 20) works this way: a response with no cost and no schedule impact is not a basis for a contract change, and a contractor that disagrees has 14 calendar days to say so in writing.

  6. 6. Answer with the fix, not a pointer

    “See architectural drawings” is not an answer. A useful response cites the sheet and spec section it relies on and adds a sketch when the fix needs one. Navigant notes that a hand drawn sketch may be enough for a new or revised detail, and may speed the response up.

  7. 7. Put every answer back into the drawings

    An answer that lives only in the log is invisible to the next trade that opens the set. Navigant recommends working every RFI response into the design drawings as the RFI is processed. Issue it as a supplemental instruction or a revised sheet, and write that reference in the Resolution column.

  8. 8. One owner for the log, reviewed every week

    Navigant recommends a single RFI coordinator who receives every RFI the day it arrives, checks that it really is an RFI and tracks it to an answer. The red dates in the log are that person's weekly agenda.

Some RFIs are coordination conflicts that a model review can catch before the set goes out; if your team works in BIM, the BIM execution plan template covers how coordination is planned. And questions about doors, frames and hardware are easier to answer when every opening sits in one table: see the door schedule template.

Fewer RFIs start with a complete set of construction documents.

WorldTeams builds remote teams for US architecture firms: drafters, Revit technicians and BIM professionals who produce and coordinate construction documents inside your standards, working your hours.

Questions, answered

What is an RFI in construction?

An RFI, or request for information, is a written question from the contractor to the architect or engineer about the contract documents: a conflict between drawings, missing information, or a detail that cannot be built as drawn. Under the AIA's A201 general conditions, the contractor reports the errors and omissions it finds as RFIs, and the architect answers in writing. Each RFI gets a number and a line in the RFI log.

Ask AI

Who writes an RFI, and who answers it?

The general contractor usually writes and sends RFIs, including the questions its subcontractors raise, and some contracts accept RFIs only from the prime contractor for that reason. The architect answers, and brings in the structural or MEP engineer when the question falls in their scope. Copy the owner's representative whenever an answer may affect cost or time, so nobody learns about it from an invoice.

Ask AI

How long should an RFI response take?

As long as the contract says. AIA A201 asks the architect to answer within the time limits agreed or, failing that, with reasonable promptness, so it pays to write a number into Division 01. The Navigant Construction Forum suggests about 10 working days as a typical target, and its study of 1,362 projects measured a median reply time of 9.7 days.

Ask AI

What is the difference between an RFI and a submittal?

An RFI asks a question about the contract documents. A submittal, such as shop drawings, product data or samples, shows how the contractor proposes to meet them, and the architect reviews it and stamps an action. Track RFIs in an RFI log, in number order, and submittals in a submittal log, sorted by spec section. Our submittal log template covers the second one.

Ask AI

Does an RFI response change the contract price or schedule?

Not by itself. An RFI answer clarifies the documents. If the contractor believes an answer adds cost or time, AIA A201 sends that through the claims process of Article 15 (Section 3.2.4), and the change itself is made by change order. That is why this template asks for a cost and schedule impact on every RFI, both when it goes out and when the answer comes back.

Ask AI

Is this RFI template free?

Yes. The form and the log are on this page to read and copy, and the Excel file is free after a short form with your name, email, phone and role. It is a standard .xlsx with no macros: a How to use sheet, the one page RFI form, and the log with dropdowns, date checks, a days open count and an overdue flag.